homework
Brightstar Industries
You will lead a training session for new employees at Brightstar Industries. You must develop a specific schedule for the following tasks (the estimated duration is shown in parentheses):
First, you need to contact the participants and explain their roles (1 day). Then you must obtain ap- proval from their department managers (3 days).
After you obtain the approval, two tasks can begin at the same time: you can arrange the meeting room (1 day) and prepare an agenda for the initial session (8 days).
When the agenda is ready, you can start two more concurrent tasks: prepare the information pack- ets (3 days) and create visual aids (6 days).
When the meeting room is arranged and the information packets are ready, you can send out an e-mail to participants (1 day).
Finally, after the e-mail is sent to participants and the visual aids are ready, you can conduct the JAD sessions (7 days). Tasks
Prepare a list showing all tasks and their durations.
Analyze the fact situation carefully to determine which tasks are concurrent and which ones depend on other tasks.
Develop a PERT/CPM chart that shows the project. Use a format similar to Figure 3-18 on page 82. Use project management software if it is available.
What is the critical path for this project? How do you know?
Solution Preview
Bright star employee training schedule of tasks
List of tasks and time
- Making contact with participants and explaining roles- 1 day
- Obtaining approval from respective department managers- 3 days
- Arrangement of the meeting room- 1 day
- Preparation of an agenda for the first session- 8 days
- Preparation of information packets-3 days
(310 words)