project management case study

project management case study

This is a case study for project management, there are four questions in the case.

I uploaded two pictures for the assignment.

 

 

 

 

Solution Preview

QUESTION 2
Total number of days for thrift = 3+2+2+3+1+1+4+1+4=21days
Remaining days to deadline = 35-21=14days
Probability issues will be sent out on time =14/35= 0.4 or 40%

(81 words)